Technical update

The numerical worked example previously published on this page is temporarily unavailable pending review of its assumptions and calculations. This page explains the information and review steps needed for a project-specific seismic anchor calculation.

Documented inputs and a consistent code basis help reviewers follow a seismic anchor calculation. ASCE 7-22 Chapter 13 restructured the component force provisions, and anchorage checks are governed by ACI 318-19 Chapter 17. The workflow below is the sequence of information gathering, engineering decisions, and review steps behind a defensible calculation package. It is reference material, not a design method or a substitute for project-specific engineering by a licensed professional.

Step 1 — Fix the project scope and the governing code edition

Before any number is produced, establish which code edition governs: the adopted building code for the jurisdiction, the referenced edition of ASCE 7 and ACI 318, and any state or local amendments. California healthcare projects add HCAI program provisions and current PIN bulletins on top of the adopted CBC. Record the edition and amendment set on the cover sheet — a calculation that does not state its basis cannot be checked against one.

Step 2 — Document the site seismic hazard inputs

The design spectral response acceleration parameters and the site class come from a documented hazard source for the actual project coordinates, not from a nearby project or a remembered value. Capture the source, the retrieval date, the risk category assumed, and the site class basis (geotechnical report versus a default assumption stated as such). Where a site class is assumed rather than investigated, that assumption belongs in the calculation, not in an engineer's head.

Step 3 — Establish component function and importance

Whether a component is a designated seismic system, and therefore what component importance factor applies, is a project-specific determination made by the engineer of record in coordination with the design team and the authority having jurisdiction. It depends on the component's post-earthquake function, its contents, and the structure it occupies — not on the building's risk category alone. Document the reasoning, not just the resulting value. Our background article on the component importance factor covers the categories the standard describes.

Step 4 — Identify the actual component row and its coefficients

ASCE 7-22 assigns component-specific coefficients by component type and mounting condition. The engineer must read the governing standard's component table for the specific equipment being anchored — including how it is mounted, whether it is treated as rigid or flexible, and whether it is isolated — and cite the row used. A superficially similar table row may use coefficients that do not fit the actual component or mounting condition.

Step 5 — Collect the building inputs that drive amplification

Component demands depend on where the component sits in the structure and on the structure itself: attachment elevation, structural height, number of stories, the seismic force-resisting system, and the building period information the standard's height-amplification and ductility provisions require. ASCE 7-22 distinguishes period-based height amplification from building ductility effects; both need building data supplied by the structural engineer of record rather than assumed by the anchorage engineer. Our height amplification and ductility article explains what those provisions represent.

Step 6 — Derive horizontal and vertical demands, then check the bounds

The horizontal design force is computed from the governing Chapter 13 equation using the inputs above, and the standard imposes lower and upper bounds on that force. The vertical seismic effect is combined per the applicable load combinations. Each of these — the equation used, the bounds check, and the combination selected — must be shown explicitly and verified by the engineer of record for the specific project. See the bounds article for what the limits are there to accomplish.

Step 7 — Resolve demand onto the anchor group

Anchor forces follow from geometry and load path: the center of mass location, the anchor pattern and count, the base frame or curb stiffness, the direction of loading considered, and which anchors participate in tension versus shear. Where equipment is mounted on rails, isolators, or a housekeeping pad, the load path through those elements is part of the calculation. Related reading: center of gravity and overturning.

Step 8 — Apply overstrength where the standard requires it

Identify the anchorage design provisions, applicable load combinations, overstrength requirements and any permitted alternatives in the governing ASCE 7 and ACI 318 editions. The project engineer should document the demand used for each steel and concrete limit state and verify the applicable tension-shear interaction checks. See the overstrength article.

Step 9 — Bring in the anchor evaluation report and site conditions

Anchor capacities come from the manufacturer's current evaluation report for the exact anchor, diameter, embedment, base material, and installation condition — including cracked versus uncracked concrete, edge distances, spacing, concrete strength and thickness, and any seismic qualification limits stated in the report. The concrete condition assumed must match what the structural drawings and the field actually provide. Related: ACI 318-19 Chapter 17 limit states and edge distance and spacing.

Step 10 — Assemble deliverables and obtain independent review

  1. State the governing code editions, amendments, and the component table row used.
  2. Tabulate every input with its source and date, including hazard values and building data.
  3. Show the demand derivation, the bounds check, and the load combinations explicitly.
  4. Include the free-body diagram, anchor layout, and the orthogonal-direction check.
  5. Tabulate every anchorage limit state and the interaction check, citing the evaluation report tables used.
  6. List installation and inspection requirements that the calculation depends on.
  7. Have the package independently reviewed and sealed by the responsible licensed engineer before submittal.

Working through it on a real project

Our engineering tools produce preliminary coordination outputs that require project-specific engineering review before use on a submittal; see the site hazard and importance-factor worksheet for the input side of the workflow. For broader context, see Equipment Anchorage Design and Anchor Bolt Design Examples.

Have a project in progress? Send us the equipment and structural information and we will review the scope and respond with a fee and schedule proposal; engineering work proceeds under a written engagement.