HCAI Seismic Certification Timeline — Week by Week
Realistic durations for HCAI seismic certification (formerly OSHPD), broken down by program. Use this to plan submittals, equipment procurement, and construction sequencing.
OSP submittal and HCAI review: 6–10 weeks
This window covers submittal preparation, HCAI review, and back-check once an approved shake-table test report exists. Per HCAI PIN 55, an OSP is issued on the basis of approved shake-table testing — certification by analysis or experience data is outside the OSP program and, where permitted by the governing provisions, is handled through a project-specific HCAI-reviewed route instead.
- Week 0
Kickoff
Quote signed, vendor drawings + cut-sheets received, project SDS / Ip confirmed.
- Week 1–2
Analysis
Center of gravity, anchorage forces per ASCE 7-22 Ch.13, anchor design per ACI 318-19 Ch.17.
- Week 3–4
Calculation package
PE/SE stamped calc set + anchorage details drafted, internal QC review.
- Week 5–8
OSP submittal
HCAI submittal, agency review, response to back-check comments.
- Week 9–10
OSP number issued
OSP record activated and added to the searchable HCAI database.
OSP + AC156 shake table testing: 14–20 weeks
Active equipment, Ip = 1.5 with post-earthquake function — generators, pumps, switchgear, fans on isolators.
- Week 0
Lab slot reserved (often 6–10 weeks out).
- Week 4–8
Test plan + RRS curve developed; equipment shipped to lab.
- Week 10–14
Witness test, post-test inspection, certificate of compliance issued.
- Week 14–20
Test report rolled into OSP submittal; HCAI back-check + final number.
See our AC156 shake table testing service for what we handle directly versus the lab.
Project anchorage package: 5–10 business days
If the component only requires project-specific anchorage/support design, a stamped anchorage package may be sufficient. If the component is subject to Special Seismic Certification, anchorage calculations alone do not satisfy SSC; an applicable OSP or an HCAI-approved project-specific SSC is also required.
- 5–10 business day standard turnaround
- Rush turnarounds available on request
- ASCE 7-22 + ACI 318-19 compliant
- Reissue at no charge if project SDS changes
Related guides
HCAI certification cost
2026 price ranges for OSP, OPM, AC156, and project letters.
ReadOSP vs OPM
Pick the right HCAI program for your equipment.
CompareHCAI OSP overview
Full program details and what we deliver.
OpenHCAI PCS preapproval
Prefabricated components & systems for CA hospitals + free PCS database.
OpenReserve your project slot
Lab slots and HCAI back-check windows fill up. The earlier we kick off, the tighter your overall schedule.
Frequently asked questions
- How long does HCAI OSP certification take?
- Plan on 14–20 weeks. An OSP is issued on the basis of approved shake-table testing per HCAI PIN 55, so the schedule includes lab booking, equipment shipping, witnessed AC156 testing, report preparation, HCAI review, and back-check. The HCAI submittal and review portion alone typically runs 6–10 weeks once a complete, test-based package is ready.
- How fast can a project anchorage package be issued?
- A stamped project-specific anchorage/support package is typically delivered in 5–10 business days once equipment cut-sheets and project seismic parameters are provided. Anchorage design is a separate scope from Special Seismic Certification and does not satisfy SSC on its own.
- What slows HCAI seismic certification down?
- The biggest delays come from incomplete vendor drawings, missing center-of-gravity data, late shake table lab booking, and HCAI back-checks. None are an engineering problem — they are a documentation problem.
Related guides in this topic hub
Continue through the connected code, certification, and design references.
