HCAI Seismic Certification Timeline — Week by Week

Realistic durations for HCAI seismic certification (formerly OSHPD), broken down by program. Use this to plan submittals, equipment procurement, and construction sequencing.

OSP pre-approval (analysis only): 6–10 weeks

Passive equipment, Ip = 1.0 or 1.5. Most chillers, AHUs, tanks, transformers, and medical gas skids fit this path.

  1. Week 0

    Kickoff

    Quote signed, vendor drawings + cut-sheets received, project SDS / Ip confirmed.

  2. Week 1–2

    Analysis

    Center of gravity, anchorage forces per ASCE 7-22 Ch.13, anchor design per ACI 318-19 Ch.17.

  3. Week 3–4

    Calculation package

    PE/SE stamped calc set + anchorage details drafted, internal QC review.

  4. Week 5–8

    OSP submittal

    HCAI submittal, agency review, response to back-check comments.

  5. Week 9–10

    OSP number issued

    OSP record activated and added to the searchable HCAI database.

OSP + AC156 shake table testing: 14–20 weeks

Active equipment, Ip = 1.5 with post-earthquake function — generators, pumps, switchgear, fans on isolators.

  1. Week 0

    Lab slot reserved (often 6–10 weeks out).

  2. Week 4–8

    Test plan + RRS curve developed; equipment shipped to lab.

  3. Week 10–14

    Witness test, post-test inspection, certificate of compliance issued.

  4. Week 14–20

    Test report rolled into OSP submittal; HCAI back-check + final number.

See our AC156 shake table testing service for what we handle directly versus the lab.

Need it faster? Project anchorage letter: 5–10 business days

For one-off installs that don't need a reusable HCAI listing, a project-specific seismic anchorage letter is the fastest legal path. PE/SE stamped, accepted at HCAI plan-check.

  • 5–10 business day standard turnaround
  • Rush turnarounds available on request
  • ASCE 7-22 + ACI 318-19 compliant
  • Reissue at no charge if project SDS changes